Goodmorning,
I have the following issue.
We are producing materials and store them in SAP on a HU. As the warehouse is to small, we need to move those HU's from time to time to an other plant/warehouse, where they do have capacity to temporarly store it.
So we create a PO put it on delivery and ship it as we would ship to a customer.
Goods are received in the other warehouse and brought on stock.
Later on when goods are needed in the original plant a new PO is created to move the stock back. So PO -> delivery -> shipped back to original Warehouse.
When i want to do the GR of that same pallet, i get a message it has allready been Goods Issued.
I do not want to relable every pallet comming back, so i was wondering if there is an other option to just take that same pallet back onto stock in its oringinal plant/warehouse.
Thanks for any help